bond update

Elementary School

• Demolition of the existing roof is complete

• Installation of new shingles is progressing

• New classroom ceiling installation has started

• Roofing is on track to finish ahead of schedule!

Middle School

• Pre-bid meeting for early work package was on July 16th and subcontractor bids are due August 5th

• Early excavation work to start middle of September

• Stay tuned for a groundbreaking ceremony on September 10th!

High School

• Roofing demolition is complete on the classroom wing and the new gym

• New roofing on the classroom wing complete by end of July

• Gym roof will be complete by middle of August

Looking ahead to August

Elementary School

• Finish roofing and siding repairs

• Finishing ceiling and lighting upgrades in classrooms

Middle School

• Present early work grading and utility package to School District

• Prepare for groundbreaking ceremony on September 10th

High School

Finish up the remainder of roof replacement project

View the Construction Update PDF here.